Arreton Works Bulletin No 6
Introduction
This is the sixth works bulletin for Arreton. Other than a
minor delay this week due to inclement weather, works are progressing to plan.
Please see the update below on the current and upcoming phases.
Progress to Date
Since starting the works on the 20th of April 2015, the
weather has been kind to us and works have progressed well. This means that we
are currently ahead of programme and anticipate the completion of the
carriageway works to be during the mid to later part of June, if we continue at
the rate we have managed to date. Although this is good news it needs to be
tempered with the thought that weather and factors such as material production
may have an impact on progress. We will provide further information on progress
to date in the next bulletin.