Monday, 18 May 2015

2015 – Arreton Roadworks – Island Roads Bulletin No: 5

Below is the Island Roads Arreton works bulletin No: 5, But due the weather (Raining today) Phase 3 may be late in completing.

Arreton Works Bulletin No 5

Introduction
This is the fifth works bulletin for Arreton, where we will try and keep you informed of the developments on site. Works continue to progress well and weather permitting, we are hoping to complete Phase 3 by the end of the day on Tuesday 19th May 2015 and commence Phase 4 on the evening of Tuesday 19th May 2015.

Phases
• Phase 1 - Arreton Cross – Adjacent to property ‘Sun Trap’.
• Phase 2 - Adjacent to property ‘Sun Trap’ to north side of access to Cherry Wood View.
• Phase 3 - South side of Cherrywood View to north side of Hazely Combe.
• Phase 4 - South side of Hazely Combe to Heasley Lane.
• Phase 5 – Heasley Lane to north side of Stickworth Lane.
• Phase 6 – South side of Stickworth Lane to Hale Common.


Junction Resurfacing
We are pleased to inform you that we completed the junction of Hazely Combe during the evening of Wednesday 13th May 2015.


The next junction, Heasley Lane, is very wide, therefore we will be resurfacing this in two halves as we complete phase 3 and commence phase 4. Access will be maintained at all times, albeit from one end of Arreton or the other.