Below is the Island Roads Arreton works bulletin No: 5, But
due the weather (Raining today) Phase 3 may be late in completing.
Arreton Works Bulletin No 5
Introduction
This is the fifth works bulletin for Arreton, where we will
try and keep you informed of the developments on site. Works continue to
progress well and weather permitting, we are hoping to complete Phase 3 by the
end of the day on Tuesday 19th May 2015 and commence Phase 4 on the evening of
Tuesday 19th May 2015.
Phases
• Phase 1 - Arreton Cross – Adjacent to property ‘Sun Trap’.
• Phase 2 - Adjacent to property ‘Sun Trap’ to north side of
access to Cherry Wood View.
• Phase 3 - South side of Cherrywood View to north side of
Hazely Combe.
• Phase 4 - South side of Hazely Combe to Heasley Lane.
• Phase 5 – Heasley Lane to north side of Stickworth Lane.
• Phase 6 – South side of Stickworth Lane to Hale Common.
Junction Resurfacing
We are pleased to inform you that we completed the junction
of Hazely Combe during the evening of Wednesday 13th May 2015.
The next junction, Heasley Lane, is very wide, therefore we
will be resurfacing this in two halves as we complete phase 3 and commence
phase 4. Access will be maintained at all times, albeit from one end of Arreton
or the other.